What is the laying on site procedure of a Bathroom Pod?

Bathroom pods can be positioned from the top (before each slab) during the construction of the building. Otherwise they can be positioned sideways (horizontally through a taxiway). The positioning of a Bathroom Pod can be done when the structure of the building has been completed but before starting the installation of external walls and facilities. Generally the first solution is the most economical one, but it requires horizontal, prefabricated...

Are there any guidelines available for placing the modules?

Of course. Before delivery we provide a general method statement which illustrates the two typical methods of placement of the pods into the building. Sometimes, though, it is necessary to fine-tune this method statement because of the peculiarity of some projects.

Is it possible to assemble a Bathroom Pod directly on site?

Yes it is. If necessary, it is possible to assemble a Bathroom Pod on site but of course this procedure results more expensive.

Are there any guidelines available to set the release height and the leveling?

Leveling points are responsibility of the installation team and a laser level should be used to make sure the correct height and levelings are set to the various loading points. 

How can a lack of horizontality of the slab be reduced?

By use of neoprene (hard rubber) pads, as loading points, which we supply at each bathroom pod delivery. 